Establishing a Start-Up Dental Practice in Downtown Seattle
Dr. Bridget Singh
Last updated
The outcome, at a glance
- Lower scheduled base rent
- ~10%Over the initial term, compared with the landlord’s initial counterproposal.
- Additional improvement funding
- >15%Compared with the landlord’s initial counterproposal.
- From engagement to opening
- ~16 monthsIncluding site selection, design, permitting, construction and fixturization.
Summary
Dr. Bridget Singh engaged Union Street to establish a start-up dental practice in a downtown Seattle retail location. After evaluating five proposals, Union Street secured space at Metropolitan Tower, used preliminary construction pricing to improve the economics, and negotiated approximately 10% lower scheduled base rent and more than 15% additional improvement funding. The lease included protections for pandemic-related delays, greater operating flexibility, and provisions supporting future transfers and financing. Union Street continued coordinating permitting, construction-related matters, improvement reimbursements, and signage through the pre-opening process, with the office established approximately 16 months after engagement.
01 / The decision
Find a location for a new dental practice.
Dr. Bridget Singh engaged Union Street on February 3, 2020, to help establish a new dental practice in downtown Seattle. The requirement was for a retail location that would permit dental use and accommodate the construction of a fully equipped office. The assignment required evaluating both the cost of occupying the space and the investment needed to prepare it for patients.
Union Street began by defining the requirement, surveying the market, and touring properties. Proposals were solicited from five alternatives before the search focused on Metropolitan Tower. The preferred space was in warm-shell condition, providing a starting point for the practice’s design but requiring substantial tenant improvements.
02 / The strategy
Connect construction planning and lease negotiations.
By the end of March, the parties had reached agreement on basic business terms. The tenant then commissioned a test-fit space plan with pricing notes, which was shared with a contractor for rough order of magnitude, or ROM, construction pricing. This preliminary budget helped establish the tenant’s anticipated investment and provided a basis for another push on the landlord’s economics, recognizing the value the practice’s improvements would add to the building.
The negotiations also took place during the onset of the COVID-19 pandemic. Construction restrictions, permitting delays, and uncertainty around opening a new business made commencement provisions particularly important. Union Street negotiated additional force majeure language addressing qualifying governmental and permitting delays, along with a more flexible commencement structure.
With preliminary construction pricing and negotiated lease economics in hand, Union Street prepared a final financial analysis before the tenant committed to the lease. The lease was provided in late July and negotiated for 6 weeks. Within seven months after Union Street’s engagement, the lease was executed, and the focus became getting the space ready for occupancy.
Compared with the landlord’s initial counterproposal, the final agreement reduced scheduled base rent over the initial term by approximately 10% and increased the improvement allowance by more than 15%. Lower fixed annual rent increases, additional base rent abatement, and initial operating expense relief helped manage the practice’s start-up costs.
The lease negotiations also addressed retail provisions that did not fit a dental office’s operations. Union Street secured the removal of double-rent penalties associated with delayed opening and interruptions in continuous operations, strengthened operating expense review rights, and negotiated flexibility for qualifying office-sharing arrangements. Transferable renewal rights and lender protections supported the practice’s long-term planning and financing needs.
03 / What changed
Continue through the pre-opening process.
Union Street’s involvement continued after execution. Over the following seven months, it helped arrange pre-construction meetings, coordinated the landlord and tenant’s architect on permitting and change-of-use applications, reconciled tenant improvement distributions, and facilitated landlord review of signage and window graphic designs. The tenant improvements were completed on time in April 2021.
The assignment combined site selection, competitive proposals, construction budgeting, financial analysis, and lease negotiations with continued coordination through the pre-opening process. This gave Dr. Singh a defined real estate commitment and a lease structured around the needs of a start-up dental practice during an unusually uncertain period. The whole process from Union Street’s engagement to identifying, securing, building out, and opening the start-up dental office, including complete design, permitting, construction, and fixturization took about 16 months.
Start with the business question
What does your next space need to solve?
Contact Union Street to discuss the timeline that you should expect for opening up your start-up’s new location.